  DATE SUBJECT Project Milestones  
01 W Jan 20 Introduction   01
02 M Jan 25 AASHTO Design   02
03 W Jan 27 AASHTO Design   03
04 M Feb 01 AASHTO Design   04
05 W Feb 03 Traffic   05
06 M Feb 08 Seminar – Colleen Kissane, CONNDOT Project 1 - Assigned 06
07 W Feb 10 Traffic   07
08 M Feb 15 Project Day   08
09 W Feb 17 Soil Properties   09
10 M Feb 22 Subgrade   10
11 W Feb 24 Base and Sub-base   11
12 M Mar 01 Asphalt Binder Project 1 - Due, Project 2 - Assigned 12
13 W Mar 03 Asphalt Binder   13
14 M Mar 08 Asphalt Binder   14
15 W Mar 10 Project Day   15
16 M Mar 22 Mid-Term Exam   16
17 W Mar 24 Asphalt Concrete Mix   17
18 M Mar 29 Asphalt Concrete Mix Project 3 - Assigned 18
20 W Mar 31 Asphalt Concrete Mix   20
21 M Apr 05 Drainage Project 2 - Due 21
22 W Apr 07 Drainage   22
23 M Apr 12 Frost Heave   23
24 W Apr 14 Pavement Distress   24
25 M Apr 19 No Class   25
26 W Apr 21 Pavement Evaluation

Seminar - Ed Block, CONNDOT

  26
27 M Apr 26 Seminar – Charles Dougan Project 3 - Due 27
28 W Apr 28 Final Exam   24

 

TEXT: Huang, Yang, Pavement Analysis and Design, Prentice-Hall, 1993

 

GRADES

Exams 60 %

Homework 10 %

Project 30 %

 

LATE ASSIGNMENTS WILL BE PENALIZED IN THE ABSENCE OF A PRIOR ARRANGEMENT. Please be punctual.

 